North Dakota PSC approves crude oil pipeline

2014-01-04T18:36:00Z North Dakota PSC approves crude oil pipelineThe Associated Press The Associated Press
January 04, 2014 6:36 pm  • 

BISMARCK, N.D. — The North Dakota Public Service Commission has approved a siting permit for the Bakken Oil Express crude oil pipeline between Killdeer and Dickinson.

The commission said the permit allows the company to begin construction of the 38-mile pipeline. The 16-inch pipeline will originate at a tanker truck unloading and pumping facility near Killdeer and transport oil to an existing Bakken Oil Express rail facility west of Dickinson.

The $14 million pipeline will have a maximum capacity of 165,000 barrels a day, which the PSC says is the equivalent of eliminating up to 825 tanker trucks a day from North Dakota Highway 22.

Construction is expected to take 12-14 weeks. The commission says the design, construction and operation of the pipeline will follow U.S. Transportation Department regulations.

Copyright 2015 The Associated Press. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.

View the North Dakota Industrial Commission Department of Mineral Resources Oil and Gas Division oil well daily activity reports.

For advertising opportunities in Bakken Breakout and Bakken Breakout Weekly, CLICK HERE.